Sprint Status

This is a fast situational awareness check, not a sprint review. It reads the

current sprint plan and story files, scans for status markers, and produces a

concise snapshot in under 30 lines. For detailed sprint management, use

/sprint-plan update or /milestone-review.

This skill is read-only. It never proposes changes, never asks to write

files, and makes at most one concrete recommendation.


1. Find the Sprint

Argument: $ARGUMENTS[0] (blank = use current sprint)

  • If an argument is given (e.g., /sprint-status 3), search

production/sprints/ for a file matching sprint-03.md, sprint-3.md,

or similar. Report which file was found.

  • If no argument is given, find the most recently modified file in

production/sprints/ and treat it as the current sprint.

  • If production/sprints/ does not exist or is empty, report: "No sprint

files found. Start a sprint with /sprint-plan new." Then stop.

Read the sprint file in full. Extract:

  • Sprint number and goal
  • Start date and end date
  • All story or task entries with their priority (Must Have / Should Have /

Nice to Have), owner, and estimate


2. Calculate Days Remaining

Using today's date and the sprint end date from the sprint file, calculate:

  • Total sprint days (end minus start)
  • Days elapsed
  • Days remaining
  • Percentage of time consumed

If the sprint file does not include explicit dates, note "Sprint dates not

found — burndown assessment skipped."


3. Scan Story Status

First: check for production/sprint-status.yaml.

If it exists, read it directly — it is the authoritative source of truth.

Extract status for each story from the status field. No markdown scanning needed.

Use its sprint, goal, start, end fields instead of re-parsing the sprint plan.

If sprint-status.yaml does not exist (legacy sprint or first-time setup),

fall back to markdown scanning:

  1. If the entry references a story file path, check if the file exists.

Read the file and scan for status markers: DONE, COMPLETE, IN PROGRESS,

BLOCKED, NOT STARTED (case-insensitive).

  1. If the entry has no file path (inline task in the sprint plan), scan the

sprint plan itself for status markers next to that entry.

  1. If no status marker is found, classify as NOT STARTED.
  2. If a file is referenced but does not exist, classify as MISSING and note it.

When using the fallback, add a note at the bottom of the output:

"⚠ No sprint-status.yaml found — status inferred from markdown. Run /sprint-plan update to generate one."

Optionally (fast check only — do not do a deep scan): grep src/ for a

directory or file name that matches the story's system slug to check for

implementation evidence. This is a hint only, not a definitive status.

Stale Story Detection

After collecting status for all stories, check each IN PROGRESS story for staleness:

  • For each story that has a referenced file, read the file and look for a

Last Updated: field in the frontmatter or header (e.g., Last Updated: 2026-04-01

or updated: 2026-04-01). Accept any reasonable date field name: Last Updated,

Updated, last-updated, updated_at.

  • Calculate days since that date using today's date.
  • If the date is more than 4 days ago, flag the story as STALE. (4-day threshold accounts for weekends — a story last touched on Friday won't appear stale until Wednesday.)
  • If no date field is found in the story file, note "no timestamp — cannot check staleness."
  • If the story has no referenced file (inline task), note "inline task — cannot check staleness."

STALE stories are included in the output table and collected into an "Attention Needed"

section (see Phase 5 output format).

Stale story escalation: If any IN PROGRESS story is flagged STALE (no progress in 4+ days), the burndown verdict

is upgraded to at least At Risk — even if the completion percentage is within the normal

On Track window. Record this escalation reason: "At Risk — [N] story(ies) with no progress in

[N] days."


4. Burndown Assessment

Calculate:

  • Tasks complete (DONE or COMPLETE)
  • Tasks in progress (IN PROGRESS)
  • Tasks blocked (BLOCKED)
  • Tasks not started (NOT STARTED or MISSING)
  • Completion percentage: (complete / total) * 100

Assess burndown by comparing completion percentage to time consumed percentage:

  • On Track: completion % is within 10 points of time consumed % or ahead
  • At Risk: completion % is 10-25 points behind time consumed %
  • Behind: completion % is more than 25 points behind time consumed %

If dates are unavailable, skip the burndown assessment and report "On Track /

At Risk / Behind: unknown — sprint dates not found."


5. Output

Keep the output concise. The story status table is mandatory — do not truncate it. Aim for under 50 lines total; omit the Emerging Risks section if nothing notable was found. Use this format:

## Sprint [N] Status — [Today's Date]
**Sprint Goal**: [from sprint plan]
**Days Remaining**: [N] of [total] ([% time consumed])

### Progress: [complete/total] tasks ([%])

| Story / Task         | Priority   | Status      | Owner   | Blocker        |
|----------------------|------------|-------------|---------|----------------|
| [title]              | Must Have  | DONE        | [owner] |                |
| [title]              | Must Have  | IN PROGRESS | [owner] |                |
| [title]              | Must Have  | BLOCKED     | [owner] | [brief reason] |
| [title]              | Should Have| NOT STARTED | [owner] |                |

### Attention Needed
| Story / Task         | Status      | Last Updated   | Days Stale | Note           |
|----------------------|-------------|----------------|------------|----------------|
| [title]              | IN PROGRESS | [date or N/A]  | [N days]   | [STALE / no timestamp — cannot check staleness / inline task — cannot check staleness] |

*(Omit this section entirely if no IN PROGRESS stories are stale or have timestamp concerns.)*

### Burndown: [On Track / At Risk / Behind]
[1-2 sentences. If behind: which Must Haves are at risk. If on track: confirm
and note any Should Haves the team could pull.]

### Must-Haves at Risk
[List any Must Have stories that are BLOCKED or NOT STARTED with less than
40% of sprint time remaining. If none, write "None."]

### Emerging Risks
[Any risks visible from the story scan: missing files, cascading blockers,
stories with no owner. If none, write "None identified."]

### Recommendation
[One concrete action, or "Sprint is on track — no action needed."]

6. Fast Escalation Rules

Apply these rules before outputting, and place the flag at the TOP of the

output if triggered (above the status table):

Critical flag — if Must Have stories are BLOCKED or NOT STARTED and

less than 40% of the sprint time remains:

SPRINT AT RISK: [N] Must Have stories are not complete with [X]% of sprint
time remaining. Recommend replanning with `/sprint-plan update`.

Completion flag — if all Must Have stories are DONE:

All Must Haves complete. Team can pull from Should Have backlog.

Missing stories flag — if any referenced story files do not exist:

NOTE: [N] story files referenced in the sprint plan are missing.
Run `/story-readiness sprint` to validate story file coverage.

Collaborative Protocol

This skill is read-only. It reports observed facts from files on disk.

  • It does not update the sprint plan
  • It does not change story status
  • It does not propose scope cuts (that is /sprint-plan update)
  • It makes at most one recommendation per run

For more detail on a specific story, the user can read the story file directly

or run /story-readiness [path].

For sprint replanning, use /sprint-plan update.

For end-of-sprint retrospective, use /retrospective.

想直接用这个技能?

本站把开放许可(MIT / Apache 等)的技能按仓库打包整理到网盘,点一下转存到你自己的网盘,不用一个个从 GitHub 拉。许可未声明的技能只给原始仓库链接,不打包。

它属于哪个仓库

星标★ 25,146
本站分层T1
该仓技能数73
原文件路径.claude/skills/sprint-status/SKILL.md

同一个仓库里的其他技能

看这个仓库的全部 73 个技能