Tooling Risk Assessment Skill

Cutting steel converts design uncertainty into cash at the worst exchange rate in hardware. This skill assesses a tooling decision the way a seasoned NPI/ME lead does: match tool class to forecast confidence, do the cavitation math against peak demand, put the T1→T2→T3 timeline on the calendar, price the "what if the design changes after tooling" scenario honestly, and write the kill criteria before the money moves.

What This Skill Produces

  • A soft vs hard tooling recommendation per part, with the tradeoff shown
  • Cavitation and capacity math against the forecast ramp
  • A T1 sample timeline with tuning-loop buffer
  • An ECO-after-tooling cost narrative (steel-safe vs weld territory)
  • Explicit kill criteria and total capital-at-risk summary

Required Inputs

Ask for these if not provided; if forecast confidence is unstated, assume it is low and label the assumption:

  • Part list going to tool — which parts, materials, cosmetic surfaces
  • Forecast — peak monthly/weekly demand and lifetime volume, with confidence
  • Design maturity — which build validated this geometry (pre-EVT? post-DVT?)
  • Cycle time estimates and target resin(s)
  • Tooling quotes if in hand — cost, cavitation, steel type, lead time
  • Hard dates — launch window that the T1 timeline must serve

Tooling Framework

Tool class tradeoff:

| | Soft tool (Al / P20 unhardened) | Hard tool (P20/H13 hardened steel) |

|---|---|---|

| Life | ~5k–100k shots | ~500k–1M+ shots |

| Lead time to T1 | ~3–6 weeks | ~8–12 weeks |

| Cost | ~30–50% of hard tool | Full cost |

| Change tolerance | Cheap to modify or scrap | Expensive; welds risk cosmetic surfaces |

| Right when | Design still moving; bridge builds; low lifetime volume | Design frozen post-DVT; high volume |

Cavitation math — show the work: parts/week/cavity = (3600 ÷ cycle-time-s) × press-hours/week × yield. Cavities needed = peak weekly demand ÷ parts/week/cavity, rounded up, plus a stated overhead for maintenance downtime. Sanity-check tool life: lifetime volume ÷ cavities vs shots-of-life; flag if a second tool is inevitable and when.

T1 timeline — T1 (first shots) at tool lead time; plan 2–3 tuning loops (T1→T2→T3) at ~2–3 weeks each for texture, warp, sink, and dimensional tuning. Cosmetic A-surfaces rarely pass at T1; do not let the schedule assume they will.

ECO-after-tooling narrative — classify the plausible changes: steel-safe (change removes steel / adds plastic — days, cheap), weld/re-machine (adds steel — weeks, risky on cosmetic surfaces), new insert or new tool (geometry change beyond repair — re-quote the lead time). State which open design questions land in which class.

Output Format

Tooling risk assessment: [product / part set]

  1. Recommendation — tool class per part, cavitation, when to kick off, capital at risk
  2. Forecast basis — the numbers used and their confidence [assumed] where inferred
  3. Capacity math — the cavitation calculation shown, tool-life check
  4. Timeline — kickoff → T1 → T2/T3 loops → parts for [build], vs the hard date
  5. Change-risk narrative — open design questions mapped to steel-safe / weld / new-tool cost
  6. Kill criteria — the specific findings (e.g. DVT reliability failure in a tooled part, forecast cut below X, cert failure implicating geometry) that stop or re-scope the tooling spend
  7. Risk register — remaining risks with owner and trigger date

Quality Checks

  • [ ] Cavitation math is shown, not asserted, and uses peak demand — not average
  • [ ] Tool life is checked against lifetime volume per cavity
  • [ ] The timeline includes tuning loops, not just T1
  • [ ] Every open design question is mapped to an ECO cost class
  • [ ] Kill criteria are specific and dated — someone could actually invoke them
  • [ ] Capital at risk is totalled, including tools that may be scrapped

Anti-Patterns

  • [ ] Do not size cavitation on average demand — peak week plus downtime overhead or the launch starves
  • [ ] Do not cut hard tools on a design that has not survived its reliability testing — that is buying a very expensive opinion
  • [ ] Do not let the schedule assume T1 parts are shippable — T1 parts are for tuning
  • [ ] Do not treat "the factory says it's fine" as a change-risk analysis — classify each open question yourself
  • [ ] Do not present a tooling recommendation without kill criteria — the moment to define "stop" is before the spend
  • [ ] Do not hide the second-tool moment — if tool life runs out mid-ramp, say when and price it now

想直接用这个技能?

本站把开放许可(MIT / Apache 等)的技能按仓库打包整理到网盘,点一下转存到你自己的网盘,不用一个个从 GitHub 拉。许可未声明的技能只给原始仓库链接,不打包。

它属于哪个仓库

星标★ 1,367
本站分层T1
该仓技能数3611
原文件路径plugins/pm-hardware/skills/tooling-risk-assessment/SKILL.md

同一个仓库里的其他技能

看这个仓库的全部 3611 个技能

同名技能的其他版本

有 3 个不同仓库或目录里都有叫 tooling-risk-assessment 的技能。它们内容并不相同,别混用: