Project Status Report Skill

Produces a clear, structured project status report — the weekly communication that keeps stakeholders informed without requiring a meeting.

Required Inputs

  • Project name
  • Reporting period
  • Current RAG status (Red / Amber / Green)
  • Key milestones (due, delivered, coming)
  • Issues or blockers
  • Decisions needed from stakeholders
  • Budget status (if tracked)
  • Audience (steering committee / sponsor / PMO / full team)

Output Structure


Project Status Report: [Project Name]

Period: [Date range] | Author: [PM] | Next report: [Date]


Overall Status

| Dimension | Status | Last period | Trend |

|---|---|---|---|

| Overall | Red / Amber / Green | [Last] | Improving / Stable / Declining |

| Schedule | | | |

| Budget | | | |

| Scope | | | |

| Risks | | | |

RAG definitions:

  • Green: On track. No significant issues.
  • Amber: At risk. Issues identified but mitigations in place.
  • Red: Off track. Escalation or decisions required to recover.

Executive Summary

[3-5 sentences. Headline story. If it is Red, say so immediately and why. Never bury bad news after good news.]


Milestone Progress

| Milestone | Due date | Status | Comment |

|---|---|---|---|

| [Milestone] | [Date] | Complete / At risk / Delayed / On track | [One line] |

Completed this period: [What was delivered]

Due next period: [What is expected]


Issues and Blockers

[Issue title] — Critical / High / Low

  • Description: [What the issue is]
  • Impact: [What happens if unresolved]
  • Owner: [Who is resolving]
  • Action: [What is being done]
  • Resolution date: [When it will be closed]

Risks

| Risk | Likelihood | Impact | Mitigation | Owner |

|---|---|---|---|---|

| [Risk] | H/M/L | H/M/L | [Action] | [Name] |


Decisions Required

| Decision | Background | Options | Recommendation | Needed by |

|---|---|---|---|---|

| [Decision] | [Context] | [Options] | [Recommendation] | [Date] |


Budget Summary

| | Budget | Actual to date | Forecast | Variance |

|---|---|---|---|---|

| Total | £ | £ | £ | £ F/A |


Next Period Plan

[3-5 specific bullet points — what will happen next period]

Writing Rules

  • Never soften a Red status
  • Milestones are binary: complete or not complete
  • Decisions must be genuinely actionable
  • Keep to one page where possible

Quality Checks

  • [ ] Red status is stated immediately (not buried after positives)
  • [ ] Every issue has a named owner and a resolution date
  • [ ] Decisions required are genuinely actionable by the audience
  • [ ] Milestones are binary (complete or not complete — no "85% done")
  • [ ] Executive summary can stand alone for a stakeholder who reads nothing else

Anti-Patterns

  • [ ] Do not rate project health as Green while listing unresolved critical blockers
  • [ ] Do not report milestone progress as a percentage — milestones are binary: complete or not complete
  • [ ] Do not bury risks at the bottom — if something is high risk, it belongs in the executive summary
  • [ ] Do not leave decisions required without specifying who must decide and by when
  • [ ] Do not write an executive summary that requires reading the full report to understand — it must stand alone

Example Trigger Phrases

  • "Write a project status report for [project]"
  • "Generate a RAG status update for [project]"
  • "Write the steering committee report for [project]"