EVT/DVT/PVT Gate Review Skill

Phase gates exist because hardware mistakes compound: an issue waved through EVT costs 10× at DVT and 100× in the field. This skill runs the gate the way a strong NPI lead does — score against written exit criteria, triage every open issue as blocker or waiver, read yield with its denominator, and make a recommendation someone can be held to.

What This Skill Produces

  • A scored exit-criteria checklist for the phase under review
  • An open-issue triage table (blocker / waiver / defer) with rationale
  • A yield readout by test station with failure Pareto
  • A waiver register with class, owner, expiry, and containment
  • A go / conditional-go / no-go recommendation with the conditions written down

Required Inputs

Ask for these if not provided; run the review on partial data but mark unverifiable criteria [no data — cannot score], never assumed-pass:

  • Which gate — EVT, DVT, or PVT exit (or entry to the next phase)
  • Build results — units built, units passing, failures by test station or symptom
  • Open issue list — bugs/defects with severity and status
  • Exit criteria if the program has them; otherwise use the reference set below and say so
  • Schedule pressure — the real next-build date, so the recommendation is honest about trade-offs

Gate Framework

Reference exit criteria (adapt to the program's own if provided):

| Criterion | EVT exit | DVT exit | PVT exit |

|---|---|---|---|

| Proves | Design works (works-like) | Design is reliable & certifiable (looks-like/works-like) | Factory can build it at rate |

| Tooling | Proto/soft tooling OK | Off near-final tooling | Production tooling, production line |

| Functional yield | ≥ ~80% with failures understood | ≥ ~90% | ≥ ~95%, stable across line runs |

| Reliability | Key risks tested (thermal, drop samples) | Full reliability suite passed (drop, tumble, thermal cycle, HALT as applicable) | ORT started; Cpk ≥ 1.33 on critical dimensions |

| Certs | Pre-scan risks identified | EMC/safety pre-scans passed | Cert filings submitted/granted |

| Cost | BOM within ~10% of target | BOM within ~5%, cost-downs planned | COGS at target with yield burdened in |

| Open issues | No unresolved blockers | No blockers; waivers classed & expiring | Only Class C waivers, all with limit samples |

Issue triage. Every open issue gets exactly one bucket: Blocker (fails a criterion, fix before gate), Waiver requested (pass the gate with the defect, under discipline below), Defer (not a gate criterion — but say why).

Waiver discipline. Class A — safety/regulatory/data-loss: never waivable. Class B — functional/reliability: waivable only with named owner, expiry date (a specific build or date at which it's fixed or the program stops), and containment for affected units. Class C — cosmetic: waivable against an approved limit sample.

Output Format

Gate review: [product] — [EVT/DVT/PVT] exit

  1. Recommendation — Go / Conditional go (conditions listed, each with owner + date) / No-go (earliest re-review)
  2. Exit criteria scorecard — criterion, target, actual, pass/fail/[no data]
  3. Yield readout — units in, units out, first-pass yield per test station, top-5 failure Pareto
  4. Open-issue triage — table: issue, severity, bucket, rationale
  5. Waiver register — waiver, class, owner, expiry, containment
  6. Risks carried forward — what the next phase inherits

Quality Checks

  • [ ] Every criterion is scored pass/fail/no-data — no blanks, no assumed passes
  • [ ] Yield is reported with denominator, build population, and per-station breakdown
  • [ ] Every waiver has a class, a named owner, an expiry, and containment
  • [ ] The recommendation names its conditions explicitly — "conditional go" without conditions is a go
  • [ ] Failure Pareto covers the top failure modes, not just an aggregate number

Anti-Patterns

  • [ ] Do not report yield without the denominator and test-station breakdown — "92% yield" on 12 hand-carried units is not data
  • [ ] Do not let a waiver pass a gate without an owner and expiry date — expiry-less waivers become the product
  • [ ] Do not waive Class A (safety/regulatory) issues under any schedule pressure
  • [ ] Do not average yield across builds with different configurations
  • [ ] Do not let "conditional go" be a euphemism for go — unconditioned conditionals are the oldest gate trick
  • [ ] Do not score a criterion pass because no data contradicts it — no data is a fail-to-verify

想直接用这个技能?

本站把开放许可(MIT / Apache 等)的技能按仓库打包整理到网盘,点一下转存到你自己的网盘,不用一个个从 GitHub 拉。许可未声明的技能只给原始仓库链接,不打包。

它属于哪个仓库

星标★ 1,367
本站分层T1
该仓技能数3611
原文件路径plugins/pm-hardware/skills/evt-dvt-pvt-gate-review/SKILL.md

同一个仓库里的其他技能

看这个仓库的全部 3611 个技能

同名技能的其他版本

有 3 个不同仓库或目录里都有叫 evt-dvt-pvt-gate-review 的技能。它们内容并不相同,别混用: