Design Verification Plan and Report (DVP&R)

When to use

Use this skill when:

  • Creating a DVP for a new part design during APQP Phase 2
  • Reviewing a supplier's DVP for completeness and DFMEA alignment
  • Determining which tests are required for a specific failure mode or design characteristic
  • Tracking test completion and recording results (the "R" in DVP&R)
  • Assessing whether a design change requires additional validation testing

Prerequisites

  • DFMEA with all failure modes identified and AP ratings assigned
  • Engineering drawing with all characteristics defined
  • Customer design specifications and performance requirements
  • List of applicable standards and test methods (customer spec, ISO, SAE, etc.)

Workflow

Step 1 — Understand the DVP structure

The DVP&R is a table with one row per test. Each test must address at least one failure mode or design characteristic from the DFMEA.

The linkage rule: Every H-AP (High Action Priority) failure mode in the DFMEA must have at least one corresponding test in the DVP. If a failure mode has no test, document why (e.g., analysis-only justification with sign-off).

Step 2 — Build each DVP row

| Column | What to enter |

|--------|--------------|

| Test number | Sequential reference (e.g., DVP-001) |

| DFMEA reference | Failure mode number(s) this test addresses |

| Test name / description | Specific name of the test (not "durability test" — use "salt spray 240h per ASTM B117") |

| Test specification | Standard or specification number with version (e.g., ASTM B117-19, SAE J2530, customer spec DS-XYZ) |

| Pass/fail criteria | Exact acceptance criteria (e.g., "no rust after 240h", "burst pressure > 150 bar", "dimension within ±0.05 mm") |

| Sample size | Number of parts to test |

| Who performs | Internal lab, external accredited lab, customer lab |

| Phase | P = Prototype, PL = Pre-launch, PR = Production |

| Planned date | Date test is scheduled to complete |

| Actual date | Date test was completed |

| Result | Pass / Fail / In progress |

| Report reference | Lab report number or document reference |

| Comments | Failures, deviations, re-test requirements |

Step 3 — Determine required tests

For each DFMEA failure mode, identify the test category:

Functional / performance tests:

  • Tests that verify the product performs its intended function
  • Examples: burst pressure, tensile strength, electrical resistance, flow rate
  • Must demonstrate the product meets its design intent specifications

Environmental / durability tests:

  • Tests that simulate the product's operating environment over its design life
  • Examples: thermal cycling, salt spray, vibration, UV exposure, humidity
  • Duration and cycles must represent the design life or accelerated equivalent

Safety / regulatory tests:

  • Tests required by law, regulation, or homologation
  • Examples: ECE R10 (EMC), FMVSS standards, ECE R94/R95 (crash), REACH, RoHS
  • Must be performed by accredited lab; results must accompany PPAP

Dimensional / material tests:

  • Verification that design dimensions and material properties are achieved
  • Examples: 3D scan, CMM, tensile test, hardness test, chemical composition
  • Must reference the specific drawing characteristic or material specification

Reliability / life tests:

  • Tests that verify the product meets its reliability target (e.g., B10 life)
  • Examples: fatigue testing, accelerated aging, wear testing
  • Test plan must include correlation between accelerated test and field life

Step 4 — Populate timing per APQP phase

| Phase | Tests due |

|-------|-----------|

| Prototype (P) | Tests on design concept — functional, dimensional, preliminary environmental |

| Pre-launch (PL) | Tests on tooled parts — full environmental, durability, all safety/regulatory |

| Production (PR) | Confirmation tests on production parts — dimensional, safety, any tests with production-specific requirements |

Not all tests need to run in all phases. Focus safety and regulatory tests on Pre-launch or Production parts.

Step 5 — Track completion (the "R" in DVP&R)

Update the DVP after each test:

  • Record actual completion date
  • Record Pass/Fail result
  • For any Fail: log a DFMEA action (or open an 8D if failure escapes to customer)
  • Re-test after corrective action — reference the re-test as a new row with the original DVP number + suffix (e.g., DVP-012-R1)

At PPAP submission: all DVP tests must show "Pass" or have a documented customer-approved deviation. If a test is still in progress at PPAP submission (e.g., a long-duration life test), a formal customer deviation request must be submitted with: the test in progress, the expected completion date, the interim risk assessment, and the customer's written acceptance. The PPAP approval will be conditional until the test completes with a Pass result.

Engineering changes: If the DFMEA is updated during the design phase and adds new H-AP failure modes, the DVP must be updated to cover them before the next gate review. A DVP revision that is behind the current DFMEA revision is a gap — the DVP&R revision must match or exceed the DFMEA revision at PPAP submission.

Step 6 — Audit an existing DVP

When reviewing a supplier's or internal DVP, check:

  • [ ] Every H-AP DFMEA failure mode has at least one corresponding test
  • [ ] Test specifications reference a specific standard or document (not "internal test")
  • [ ] Pass/fail criteria are objective and measurable (not "acceptable appearance")
  • [ ] Sample sizes are adequate (not "1 sample" for durability/life tests)
  • [ ] Safety and regulatory tests are assigned to an accredited external lab
  • [ ] All results show "Pass" (or documented deviations with customer approval)
  • [ ] Failed tests have a corresponding DFMEA update or corrective action reference
  • [ ] DVP revision is aligned with the current DFMEA revision

Validation criteria

A complete DVP&R for PPAP submission must:

  • Reference every H-AP failure mode from the DFMEA
  • Have specific, standard-referenced test methods (not "per engineering judgement")
  • Show Pass results for all tests (or customer-approved deviations)
  • Have accredited lab reports for all safety/regulatory tests
  • Be signed off by design engineering and quality

Common mistakes

  • DVP created with generic tests not linked to specific DFMEA failure modes
  • Pass/fail criteria defined as "meets spec" without stating what the spec is
  • All tests assigned to internal lab when regulatory tests require external accreditation
  • DVP not updated when DFMEA adds new H-AP failure modes during design reviews
  • Re-tests after failures not documented — original Fail result erased
  • Sample size of 1 for durability or life tests (statistically meaningless)
  • DVP not updated to "Report" status at PPAP — submitted as plan, not results

Output Format

At the start of each use, ask the user:

> "How would you like to receive the output?

> A — Structured Markdown (formatted tables and sections, ready to copy)

> B — Plain tables (simplified structure for Excel or Word)

> C — Narrative report (flowing text for a formal document or email)

>

> Default: A."

Adapt all output sections to the chosen format. If the platform or session context already defines a format preference, skip this question.

Changelog

| Version | Date | Author | Change |

|---------|------|--------|--------|

| 1.0 | 2026-06-06 | @RBraga01 | Initial release |

| 1.1 | 2026-06-06 | @migmcc | Added guidance for tests in-progress at PPAP submission (customer deviation process); added DVP revision synchronisation with DFMEA requirement |

想直接用这个技能?

本站把开放许可(MIT / Apache 等)的技能按仓库打包整理到网盘,点一下转存到你自己的网盘,不用一个个从 GitHub 拉。许可未声明的技能只给原始仓库链接,不打包。

它属于哪个仓库

星标★ 1,027
本站分层T1
该仓技能数1910
原文件路径plugins/RBraga01/Quality-Engineering-Skills/skills/planning/dvp-test-plan/SKILL.md

同一个仓库里的其他技能

看这个仓库的全部 1910 个技能