VIS Workflow

Use this as the project-management skill for an IEEE VIS submission. Replace every date with the

current official timetable and work backwards from the abstract deadline — which precedes the

full-paper deadline and locks your author list. VIS publishes in IEEE TVCG, so plan for a likely

conditional-accept second round inside the review cycle, not just an accept/reject.

VIS is a conference whose full papers are journal articles: the conference has no standing

editor-in-chief, and the rotating analogue is the per-edition VIS Executive Committee, Overall Paper

Chairs, and the six Area Paper Chairs (verify the roster on the current organizing page — 待核实

beyond named chairs). The cost model is conference registration; at least one author presents.

Milestones

  • Area fit: confirm VIS over a sibling venue and pick the primary area among the six

(vis-topic-selection).

  • Evidence lock: freeze the contribution type, the design rationale, the study/benchmark design,

and the supplemental video plan.

  • Abstract: submit real title, abstract, final author list, primary area, and keywords by

the abstract deadline (VIS 2026: 21 March 2026).

  • Full paper: upload the PDF (VIS 2026: 31 March 2026); title/abstract/PDF then freeze.
  • Supplemental: finish and anonymize the video, code, and data in the one-week window (VIS 2026:

7 April 2026).

  • First-round reviews: triage each comment by criterion (novelty, impact, evidence, methodology,

encoding rationale, reproducibility).

  • Conditional accept (if issued): execute a revision plus a summary-of-changes, re-read by the

same reviewers against the required changes.

  • Decision: archive reviews, response, and every submitted version.
  • Acceptance: prepare the TVCG camera-ready, complete Open Practices disclosures, pursue the

Graphics Replicability Stamp on its own track, register, and present.

Backward plan from the paper deadline

| Weeks out (heuristic) | Visualization-paper milestone |

|---|---|

| 10+ | Contribution type fixed; data/task abstraction and design rationale settled |

| 8 | Technique/system implemented; study or benchmark designed; preregistration filed if used |

| 6 | Study run / benchmark complete; effect sizes and CIs computed; figures drafted |

| 4 | Full draft in the VGTC/TVCG template; supplemental video shot |

| 3 | Internal mock review by a visualization reader |

| 2 | Encoding rationale hardened, related-work delta sharpened, 9-page budget met |

| 1 | Abstract submitted with final authors; anonymity sweep on PDF + video (if double-blind) |

| 0 | Full PDF uploaded; supplemental finished and anonymized in its extra week |

These offsets are planning heuristics only — anchor every one to the current call, never to a

previous cycle's calendar.

The annual-cycle reality

VIS runs a single annual full-paper cycle. Two planning consequences:

  • A conditional accept has a hard second-round window. Under-budgeting the revision turns a

winnable R&R into a reject; treat the required changes as a scored deadline, not a formality.

  • Missing the annual deadline costs roughly a year at VIS; a sibling venue (EuroVis, PacificVis)

or the TVCG journal track may have a nearer date — factor that into routing rather than idling.

Failure modes by stage

  • Evidence still moving at week 4 forces last-minute studies nobody has audited — the classic

methodology reject in the making.

  • Leaving the video to the final week wastes VIS's extra supplemental week and ships an

unpolished or identity-leaking video that reviewers judge harshly.

  • Skipping the mock review forfeits the one chance to hear "your encoding is not justified" from

a friend instead of a reviewer.

  • Treating a conditional accept as an accept and under-budgeting the revision turns it into a

rejection.

  • Adding an author after the abstract deadline — not permitted; finalize authorship early.

Coordination notes

  • Assign one owner for the supplemental video/code and another for the anonymity sweep; shared

ownership is how both slip.

  • Archive the exact submitted PDF, supplemental, and (later) summary-of-changes — the second round

must quote them precisely and, if double-blind, stay anonymous through phase one.

Output format

[Current stage] idea / evidence / writing / abstract / submitted / conditional accept / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness>
[Risk register] <page budget / anonymity / evidence / encoding rationale / video / second round>
[Owner map] <task -> person or role>