PerCom Workflow

Use this as the project-management skill for a PerCom submission. Replace every date with the

current official timetable and work backwards from the HotCRP registration cutoff — which

precedes the paper deadline by about a week. PerCom runs a single annual deadline feeding one

review round with a bounded rebuttal and an early-rejection gate; there is no journal-style

revision, so plan for the paper to be complete at submission.

PerCom is an IEEE Computer Society conference: it has no standing editor-in-chief and no APC

in the open-access sense. Rotating leadership is the per-edition General and TPC (Program) Co-Chairs

(PerCom 2027 full roster 待核实 as of 2026-07-09), and the cost model is IEEE registration with

at least one author presenting in person.

Milestones

  • Venue fit: confirm PerCom over ACM UbiComp/IMWUT, MobiCom, SenSys, or IPSN, and confirm the

paper is ready this cycle (percom-topic-selection).

  • Data collection lock: IRB/consent secured, subjects recruited, sensing protocol frozen — the

long pole for a human-subjects paper.

  • Evidence lock: freeze claims, cross-subject splits, baselines, metrics, limitations, and the

dataset contents. Nothing can be added in the rebuttal.

  • Registration: submit real title, abstract, authors, topics by the earlier registration

deadline (PerCom 2027: 4 Sep 2026).

  • Submission: upload the anonymized PDF and the open-data plan (PerCom 2027: 11 Sep 2026 AoE).
  • Early-rejection gate: notification (~20 Nov 2026) either early-rejects or invites a rebuttal.
  • Rebuttal (if invited): answer explicit reviewer questions from existing evidence, anonymously

(~26 Nov 2026).

  • Decision: accept/reject (~18 Dec 2026); archive reviews, rebuttal, and every submitted

version.

  • Acceptance: prepare the IEEE Xplore camera-ready (PDF eXpress, eCopyright, ORCID), deposit the

de-identified dataset, register, and present in person.

Backward plan from the submission deadline

| Weeks out (heuristic) | Human-subjects sensing milestone |

|---|---|

| 16+ | IRB/consent approved; recruitment and data collection begun (the long pole) |

| 12 | Data collection complete; labeling protocol run with annotator agreement |

| 10 | Claims fixed; cross-subject (LOSO) splits and baselines chosen |

| 8 | Experiments complete; F1/event-level results with per-subject spread computed |

| 6 | Analysis done; limitations drafted alongside results; dataset de-identified |

| 4 | Full draft in the IEEEtran 9+1 template; artifact assembled and anonymized |

| 3 | Internal mock review by a ubicomp reader ("is this within-subject only?") |

| 2 | Limitations hardened, related-work delta sharpened, 9-page budget met |

| 1 | Double-blind sweep on PDF and dataset link; open-data plan final |

| 0 | Registration by its earlier cutoff, then paper + dataset link on HotCRP |

These offsets are planning heuristics only — anchor every one to the current Important Dates page,

never to a previous cycle's calendar. Note the 16-week IRB/collection pole: human-subjects data

cannot be rushed in the final month.

Cycle reality: one shot per year, gated early

PerCom runs one annual research deadline. As of 2026-07-09, PerCom 2026 (Pisa) has concluded, so the

live next target is PerCom 2027 (Goa; deadline 11 Sep 2026). Two planning consequences:

  • There is no revision cycle. A paper that is not complete — especially one lacking cross-subject

evidence — cannot be rescued in the rebuttal; it will likely be early-rejected. Finish the

evaluation before submitting.

  • Missing the annual deadline costs roughly a year at PerCom; ACM IMWUT has rolling

quarterly deadlines and a revise cycle, so a paper that needs another round of experiments may be

better routed there than held for a year — factor that into routing rather than idling.

Failure modes by stage

  • IRB or recruitment slipping pushes data collection into the final month and forces a

within-subject-only evaluation — the classic PerCom early-reject in the making.

  • Discovering at week 3 that the split was within-subject is fatal with no time to recollect;

design the LOSO split at week 10.

  • Leaving the anonymized dataset to the final week is how a testbed name, a re-identifying photo,

or an owner string leaks identity under double-blind review.

  • Skipping the mock review forfeits the one chance to hear "your evaluation is within-subject"

from a friend instead of a reviewer — and there is no revision to fix it.

  • Treating the rebuttal as a revision and planning to "add the experiment then" — the process

neither expects nor permits it.

Coordination notes

  • Assign one owner for IRB/consent and the dataset, and another for the double-blind anonymity

sweep; shared ownership is how both slip.

  • Archive the exact submitted PDF, dataset, and (later) rebuttal — the discussion must quote them

precisely and stay anonymous.

Output format

[Current stage] idea / IRB+collection / evidence / writing / registration / submitted / rebuttal / accepted
[Next official deadline] <date and source, or unknown>
[Critical path] <three tasks that determine readiness -- IRB/collection is usually one>
[Risk register] <IRB / cross-subject evaluation / 9-page budget / anonymity / dataset / presentation>