FAST Workflow

Use this as the project-management skill for a FAST submission. Replace every date with the current

official timetable and work backwards from the deadline you choose. FAST — the USENIX Conference on

File and Storage Technologies — runs two deadlines a year, has an author-response period,

and can issue a one-shot revision that spans into the next deadline, so plan for a longer arc

than a plain accept/reject conference.

FAST is a USENIX conference: it has no standing editor-in-chief and **no article-processing

charge**. Rotating leadership is the per-edition Program Co-Chairs and the program committee, and

the cost model is registration plus USENIX membership — proceedings are open access. Chairs and the

Artifact Evaluation Committee rotate yearly; re-check the current committee page rather than carrying

a name forward (FAST '27 rosters: 待核实 beyond what the CFP names).

Choose the deadline, then plan backward

FAST '27 offers Spring (submit 17 Mar 2026, notify 4 Jun 2026, final files 28 Jul 2026) and

Fall (submit 15 Sep 2026, notify 8 Dec 2026, final files 26 Jan 2027). Pick by *evidence

readiness* — storage measurements at steady state on real, aged devices take real calendar time —

not by whichever is nearest. As of 2026-07-09 the Spring round is notified and the live target is

the Fall deadline, 15 Sep 2026.

Milestones

  • Venue fit: confirm FAST over OSDI/ATC/EuroSys and that the core lesson is storage

(fast-topic-selection).

  • Evidence lock: freeze the testbed (devices, firmware, kernel), the workloads/traces, the

device-state protocol (aging, fill, TRIM), the baselines, and the metrics.

  • Registration: register real title, abstract, authors, topics, and conflicts on the correct

Spring/Fall HotCRP instance.

  • Submission: upload the anonymized, double-blind PDF and the availability statement.
  • Author response: during the response window, answer reviewer questions with existing evidence

or a concrete, feasible plan.

  • Decision: Accept / Accept-with-shepherding / One-shot Revision / Reject.
  • Shepherding or one-shot revision (if issued): make the required changes; a one-shot revision

may demand new experiments and is resubmitted at the next deadline.

  • Acceptance: prepare the open-access camera-ready, pursue USENIX artifact badges on the AEC's

own timeline, register, and present.

Backward plan from the submission deadline

| Weeks out (heuristic) | Storage-evaluation milestone |

|---|---|

| 12+ | Testbed fixed: device models/firmware, kernel, mkfs options; workloads/traces chosen |

| 10 | Device-state protocol locked (aging/preconditioning, fill level, TRIM); baselines built and tuned |

| 8 | Measurement runs complete at steady state; device counters (SMART/logs) captured; provenance logged |

| 6 | Analysis done; tail-latency distributions, write-amplification, endurance projections computed |

| 4 | Full draft in the USENIX template; artifact + trace-replay scripts assembled and anonymized |

| 3 | Internal mock review by a storage reader |

| 2 | Caveats hardened, related-work delta sharpened, page limit met |

| 1 | Double-blind sweep on PDF and artifact; availability statement final |

| 0 | Register the abstract on the correct HotCRP, then upload |

These offsets are planning heuristics only — anchor every one to the current Important Dates block,

never to a previous cycle's calendar. Note that storage runs (aging a drive, replaying a long trace,

an endurance test) can dominate the schedule; size them explicitly.

The two-deadline reality and one-shot revision

  • Missing one deadline is not a lost year. The other FAST deadline is months away — but so is a

sibling (OSDI/ATC/EuroSys) date; factor that into routing rather than idling.

  • A one-shot revision is a second full deadline, not a formality. Its instructions can require

specific new experiments, the revised paper is re-read, and it can be rejected. Budget the

revision window like a fresh submission, and note the paper stays under review at FAST during it,

so it cannot go elsewhere in parallel.

Failure modes by stage

  • Testbed still moving at week 6 forces last-minute measurements nobody audited — the classic

storage-soundness reject in the making.

  • Reporting fresh-out-of-box instead of steady-state numbers invites the "did you precondition?"

objection that can sink an SSD paper.

  • Leaving the anonymized artifact and trace hosting to the final week is how a device dump,

hostname, or personal trace URL leaks identity under double-blind.

  • Treating a one-shot revision as an accept and under-budgeting its experiments turns a winnable

revision into a reject.

Coordination notes

  • Assign one owner for the testbed/provenance log and another for the double-blind sweep; shared

ownership is how both slip.

  • Archive the exact submitted PDF, artifact, and (later) the response/revision documents — the

revision round must quote reviews precisely and stay anonymous.

Output format

[Current stage] idea / evidence / writing / registration / submitted / response / shepherd-or-revision / accepted
[Target deadline] Spring / Fall <date and source, or unknown>
[Critical path] <three tasks that determine readiness — often measurement-time-bound>
[Risk register] <page limit / anonymity / device state / provenance / tail latency / artifact>