Spec to Repo

A delivery-focused skill that bridges product spec to repository work.

Where PRD-writing skills focus on what to build, this skill focuses on

how to break it down for execution — the ticket decomposition,

branch strategy, PR sequencing, and acceptance criteria that make a

spec actually ship.

When to use this skill

  • Translating a PRD or feature brief into a sequence of tickets
  • Designing the branch + PR sequence for a multi-week feature
  • Auditing an existing ticket decomposition for risk (big tickets, hidden dependencies)
  • Defining definition-of-done that covers code, tests, docs, telemetry
  • Planning incremental shipping (feature flags, canaries, dark-launch)
  • Reviewing a decomposition before sprint planning to avoid mid-sprint surprises

Inputs the advisor expects

  • The PRD or spec document
  • Target ship window (1 sprint? 1 month? 1 quarter?)
  • Engineering team size + composition (FE, BE, ML, mobile)
  • Risk profile (greenfield vs production-impacting)
  • Feature-flag and rollout posture

Clarify First

Before generating the repo plan, confirm these inputs. If any is unknown or vague, ASK — do not assume:

  • [ ] The PRD or spec — the user-facing capabilities to decompose (drives the epic→ticket tree)
  • [ ] Target ship window — one sprint, month, or quarter (drives ticket sizing and PR sequencing)
  • [ ] Team composition — FE, BE, ML, mobile (decides parallel paths and vertical-slice tickets)
  • [ ] Feature-flag and rollout posture — flagged/dark-launch vs direct ship (drives PR sequencing and definition-of-done)

Stop rule: ask only the 2-3 that most change the output. If the user says "just draft it," proceed and list your assumptions at the top of the artifact.

Workflows

Workflow 1 — Decompose a PRD into tickets

  1. Pull the PRD; identify the user-facing capabilities.
  2. Run prd_to_tickets_decomposer.py with the user stories + technical

notes to surface a candidate ticket tree (epic → tickets → subtasks)

with size estimates and dependencies.

  1. Manually review; tune for team-specific patterns.
python3 spec-to-repo/scripts/prd_to_tickets_decomposer.py \
  --input prd.json --format markdown

Workflow 2 — Validate the branch and PR plan

  1. Capture proposed branch + PR sequence.
  2. Run pr_scope_analyzer.py to flag oversized PRs, missing tests,

missing telemetry, and risky merges.

  1. Adjust before opening PRs.
python3 spec-to-repo/scripts/pr_scope_analyzer.py \
  --input pr_plan.json --format markdown

Workflow 3 — Lint branch names against convention

  1. Capture branch list (e.g., git branch --list).
  2. Run branch_naming_validator.py to flag non-conformant names.
python3 spec-to-repo/scripts/branch_naming_validator.py \
  --input branches.txt --format markdown

Decision frameworks

Ticket sizing

| Size | Effort | Description |

|------|--------|-------------|

| XS | < 0.5 day | Trivial; usually skip ticketing |

| S | 0.5–1 day | One simple change |

| M | 1–3 days | Single feature, well-scoped |

| L | 3–5 days | Multi-day work; should split if possible |

| XL | > 5 days | Always split — too big for confident estimate |

A ticket that's L or XL almost always hides a missing decomposition. Push

back on yourself.

The ticket tree

Epic — large product feature ("Notifications v2")
├── Story — user-facing capability ("As a user I can mute by channel")
│   ├── Ticket — one engineering work item (backend, frontend, infra)
│   │   └── Subtask — atomic step (optional)

Most orgs:

  • Epic ≈ PRD-sized scope
  • Story ≈ one user-facing slice
  • Ticket ≈ one PR (or pair of PRs: BE + FE)

The "vertical slice"

Best ticket: ships a small user-visible improvement end-to-end.

  • Backend change + frontend change + tests + telemetry + docs in one ship
  • Better than: BE-only ticket waiting for FE-only ticket waiting for QA

When you can't slice vertically (e.g., backend is weeks before frontend):

  • Use feature flags to ship behind a switch
  • Dark-launch backend to validate before frontend
  • Communicate the lag explicitly

PR sequencing

For a multi-PR feature:

  1. PR 1 — Infrastructure / scaffolding (no behavior change)
  2. PR 2 — Backend changes (behind flag; no frontend uses it)
  3. PR 3 — Frontend changes (behind flag; tests pass with flag on/off)
  4. PR 4 — Telemetry + analytics events
  5. PR 5 — Documentation + runbook
  6. PR 6 — Flag enablement (small change; reviewable cleanly)

Each PR < 400 lines if possible. Reviewability collapses above 400.

Definition of done

Per ticket:

  • Code: written, reviewed, merged
  • Tests: unit + integration as appropriate
  • Telemetry: events fired (and verified)
  • Docs: README / runbook / API doc updated as needed
  • Accessibility: meets the project bar
  • Feature flag: configured (if applicable)
  • Rollout plan: defined for non-flagged ships

Per epic:

  • All tickets complete
  • Feature behind flag in production for 1+ week (if risky)
  • Flag enabled for X% (canary), then ramped
  • Telemetry shows expected behavior
  • Customer-facing comms drafted (if applicable)

Common engagements

"Help me decompose this PRD"

  1. List user-facing capabilities (1-line each).
  2. For each, list the backend, frontend, infra, telemetry, docs work.
  3. Estimate; flag anything > 3 days for further breakdown.
  4. Sequence: scaffolding first, behavior next, flag enablement last.
  5. Identify cross-team dependencies; engage before sprint start.

"Our team is shipping huge PRs"

  1. Audit the last 10 PRs: median size, P95 size.
  2. Identify the patterns: monolithic services + flag-less work + slow review.
  3. Pilot: feature flags + ticket-first decomposition + PR size SLA.
  4. Track: median PR size + lead time week-over-week.

"Help me plan the rollout"

  1. Define a successful launch criterion (e.g., < 0.5% error rate at 50%).
  2. Identify the kill switch (feature flag or quick-revert).
  3. Plan ramps: 1% → 5% → 25% → 50% → 100% with bake time.
  4. Define rollback criteria + comms plan.
  5. Coordinate with on-call + support.

Anti-patterns to avoid

  • Decomposition as wishful thinking. "3-day estimate" with no break-down is a 2-week-actual.
  • Sequential ticket tree (everyone waits). Plan parallel paths.
  • Hidden dependencies on other teams. Surface them in decomposition.
  • No feature flag. Shippable in chunks but every change goes to all users immediately.
  • PRs > 1000 lines. Reviewability dies; bugs hide.
  • DoD that's just "code merged." Forgets tests, docs, telemetry.
  • Ticket = a day of work. Sometimes tickets are 30 minutes; sometimes 3 days.

References

  • references/spec-to-ticket-decomposition.md — patterns for breaking specs into tickets
  • references/branch-strategy-for-features.md — branching, feature flags, dark-launch
  • references/pr-discipline-and-conventions.md — PR size, review, definition-of-done

Related skills

  • product-team/agile-product-owner — sprint planning, prioritization
  • engineering/feature-flags-architect — flag strategy
  • engineering/observability-designer — SLO / telemetry
  • c-level-advisor/vpe-advisor — broader delivery context
  • project-management/ skills — ticket / sprint management tooling